In Red Deer, a deck 24 inches or more above ground needs a building permit, a fence needs none, and a shed over 10 square metres needs two permits.
Key information
In Red Deer, a deck 24 inches or more above the ground needs a building permit, a fence does not need a permit, and a shed or garage over 10 square metres needs a development permit and a building permit. Apply through the city's MyPermits portal.

On this page
At a glance
| Project | Permit needed |
|---|---|
| Patio, 9 inches or less high | No permit |
| Deck 10 to 24 inches high | No building permit. Development permit only if you need a variance. |
| Deck 24 inches or more high | Building permit |
| Covered deck | Building permit |
| Enclosed deck | Development permit and building permit |
| Fence | No permit. Back yard up to 2 m (6 ft 6 in), front yard up to 0.9 m (3 ft) |
| Shed or garage over 10 square metres (107 sq. ft.) | Development permit and building permit |
| Shed under 10 square metres and 2.8 m (9 ft) high or lower | No permit, but it must be at least 0.9 m (3 ft) from side and rear lines |
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer
Do I need a permit for a deck?
It depends on height. A patio 9 inches or less above the ground needs no permit, and can be built up to the side and rear property lines. A deck between 10 and 24 inches high needs a development permit only if you ask for a variance to the zoning bylaw. A deck 24 inches or more above the ground needs a building permit.
A covered deck needs a building permit. An enclosed deck needs both a development permit and a building permit. Side yard setbacks run from 0.35 m (1 ft 2 in) to 0.6 m (2 ft) for decks 10 to 24 inches high, depending on your zone. For decks 24 inches or higher, the rear setback is at least 4.5 m (14 ft 7 in).
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer
What are the fence rules?
You do not need a building permit to build a fence, and no inspection is needed afterwards. Build it on or inside your property lines. Your Real Property Report shows where they are.
A back yard fence can be up to 6 feet 6 inches (2 metres) high. A front yard fence can be up to 3 feet (0.9 metres) high. Electrified materials, sharpened spikes, broken glass and barbed wire are not allowed. On a corner lot, nothing higher than 3 feet may block the sight lines, including fences and hedges. Check with your builder or developer for neighbourhood design rules.
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer
When does a shed or garage need a permit?
Sheds, gazebos, workshops, greenhouses, pergolas, carports and detached garages count as accessory buildings. If one is over 10 square metres (107 sq. ft.), or smaller but over 2.8 m (9 ft) high, you need a development permit and a building permit.
Smaller buildings need no permit but must still sit at least 0.9 m (3 ft) from the side and rear property lines. An accessory building cannot be in a front yard or over a gas line, and the maximum height is 5.0 m (16 ft 4 in) and one storey. Most properties allow 45 per cent total site coverage. Call Alberta One-Call before you dig.
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer
How do I apply, and how long does it take?
Homeowners and licensed contractors can apply through the city's MyPermits portal. If you do not own the property, include a Letter of Authorization. A development permit is usually decided 5 to 7 business days after the application is complete. If neighbours must be consulted, add about three weeks. A variance has a 21-day advertised appeal period. A building permit usually takes 7 to 10 business days, and cannot be issued before a required development permit.
The building season, April 1 to October 31, can take longer. Building permit fees change each May 1 with the Consumer Price Index, and the Safety Codes fee schedule and Development Permit Fee Bylaw list them. For help, call 403-342-8190 or email inspections@reddeer.ca. City Hall is open Monday to Friday from 8 a.m. to 4:30 p.m.
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer
Questions and answers
Do I need a permit for a fence in Red Deer?
No. You do not need a building permit and no inspection is needed, but you must follow the height and placement rules.
Source: Fences | City of Red Deer
How tall can a back yard fence be?
Up to 6 feet 6 inches (2 metres).
Source: Fences | City of Red Deer
At what height does a deck need a building permit?
24 inches or more above the ground.
Source: Decks | City of Red Deer
Does a covered deck need a permit?
Yes. A covered deck needs a building permit.
Source: Decks | City of Red Deer
Does a small shed need a permit?
Not if it is under 10 square metres (107 sq. ft.) and no higher than 2.8 m (9 ft). It must still be at least 0.9 m (3 ft) from the side and rear lines.
How long does a permit take?
Usually 5 to 7 business days for a development permit and 7 to 10 business days for a building permit, once the application is complete.
Source: Decks | City of Red Deer
Who can apply for a permit?
The homeowner or a licensed contractor. A person who does not own the property needs a Letter of Authorization.
Source: Decks | City of Red Deer
Official service and next steps
Sources: Decks | City of Red Deer · Fences | City of Red Deer · Detached Garages & Sheds | City of Red Deer